Sector: Power
  Sub-Sector / Technically Autonomous Unit (Network, basin, ..): National          
      Component Present Situation Target Situation Projects Characteristics Priority
                Technical Constraints Cost Impact Uncertainty  
Sector Sub-sector Geographic area   Sp St ∆S Description Min. delay to start Min. constr. period Unit rate Qty Investment (in Million US$) Land value / expro (a') Yearly maintenance cost (b) Major rehab/replac. cost (c ) Span for rehab/replc (d) Yearly operation cost (e) Uncertainty   (High, Medium, Low)  
                  (Year) (Year)         % %   %        
      Physical Stock                                  
        A. Generation                                                                                                                                                  
        A1. Combustibles                                                                                                                                                  
                                           
        Three steam plants running on heavy fuel One steam plant running on heavy fuel                                
        Zouk, efficiency at 35%  None (Zouk is expected to be decommissioned)                                                                                                                                                
        Jieh, efficiency at under 30% Jieh will run on natural gas as a combined cycle or steam plant Construct gas infrastructure from Selaata southwards up to Zahrani with branch to Jieh   This project should precede construction of new Jieh power plant, but it may follow construction of new LNG plant at Selaata 5 3 $1,800   $198 $0.00 2.00% 20.00% 30.00 0.50% 30%   Medium 3                                                                                                              
            Construct gas infrastructure from Zahrani northwards up to Jieh   This project should precede construction of new Jieh power plant, and it should be executed only if the arrival of gas through the floating terminal or westwards from Damascus at Zahrani is imminent, and it won't be necessary if the project above is executed 5 2 $1,200   $36 $0.00 3.00% 20.00% 30.00 0.50% 20%   High 3                                                                                                              
        Hreiche, efficiency at 30% Same                                                                                                                                                
        Two combined cycle plants running on diesel Two combined cycle plants running on natural gas                                                                                                                                                
        Deir Ammar, efficiency at 50% Deir Ammar will run on natural gas Arab gas line will have reached Homs in Syria by late 2007 (externally funded project)                                                                                                                                              
            Construction of new LNG terminal at location of new power plant, Selaata one likely location    This project is related to the timely arrival of natural gas at Deir Ammar (and onward to Selaata), and it should cater for all plants with natural gas, and its construction dictates the presence of the North-South gas infrastructure   4 2     $300 $0.00 5.00% 40.00% 30.00 20.00% 30%   High 2                                                                                                              
            Construction of gas infrastructure between Deir Ammar and Selaata   This project should precede construction of LNG terminal and power plant at Selaata, but it is justified even if LNG were not constructed, as it may be able to transmit gas in the southward direction through the Arab Line source 1 2 $1,200   $24 $0.00 2.00% 20.00% 30.00 0.50% 20%   Low 1                                                                                                              
        Zahrani, efficiency at 50% Zahrani will run on natural gas Coastal Line project mentioned above   See above                                                                                                                                          
            Completion of gas infrastructure from the Syrian border westwards up to Zahrani   This project is dependent upon implementation of the gas infrastructure project in the Syrian territory and political developments, and it won't be necessary if the North-South gas infrastructure alternative is adopted 5 3 $1,500   $120 $0.00 3.00% 20.00% 30.00 2.00% 25%   High 3                                                                                                              
        Obtain floating LNG tanker for Zahrani   This project may also benefit from the presence of the North-South gas infrastructure and cater for all coastal power plants 1 1     $70 $0.00 5.00% 0.00% --- 10.00% 25% Low 1  
        Open cycle plants running on diesel as base plants Open cycle plants running on diesel as peak plants                                                                                                                                                
        Baalbeck, 70/30 MW, efficiency at 30% Baalbeck will run on diesel but as a peak plant                                                                                                                                                
        Tyre, 70/30 MW, efficiency at 30% Tyre will run on diesel but as a peak plant                                                                                                                                                
        Installed/Actual generation capacity is 2,334/1,685 MW
Installed generation capacity should become 2,900 MW
                                 
                                             
        A2. Electrical Characteristics                                    
        Steam plants: 1,013/765 MW  Steam plants: 75 MW                                  
        Zouk, 607/475 MW Zouk is out of service and a new plant is constructed elsewhere Construction of new 1,000 MW CC plant None     $550                        
        3*145 MW +1*172 MW turbines, whose retirement date is on 2015 or before     Commission first phase before 2010 1 3     $250 $0.00 3.00% 40.00% 30.00 45.00% 20%   Low 1  
              Commission second phase before 2015 4 2     $170   3.00% 40.00% 30.00 45.00% 20%   Low 2  
                Commission third phase before 2020 10 2     $130   3.00% 40.00% 30.00 45.00% 20%   Low 3                                                                                                              
        Jieh, 331/240 MW New 435 MW  power plant at Jieh Construction of new 435 MW combined cycle plant at Jieh after 2010    Unavailability of natural gas at Zahrani or infeasibility of coastal line may result in maintaining Jieh as a steam plant      $500                                                                                                                                    
        2*62 MW turbines, which have reached the end of their life Around 40% of Jieh's output is expected to be lost in 2006 Perform basic rehabilitation measures on the 2*62 MW turbines to extend their life to the best extent possible   None 0 1     $15 $0.00 1.00% --- 10.00 60.00% 50%   Low 1                                                                                                              
        3*69 MW turbine, whose retirement date is expected on 2010 100% of Jieh's output is expected to be lost in 2010 Install the new plant equipment and commission the new plant   None 4 2     $200 $0.00 3.00% 40.00% 30.00 45.00% 30%   Low 2                                                                                                              
        Hreiche, 75/50 MW New steam plant at Hreiche with 75 MW capacity  Construction of new 75 MW steam plant prior to 2015 None 7 2 $700   $53 $0.00 3.00% 40.00% 40.00 60.00% 20%   Low 3  
        1*75 MW turbine, whose retirement date is expected on 2015                                                                                                                                                  
        Combined cycle plants: 870/820 MW Combined cycle plants: 3,175 MW (incl Jieh) Expansion of Deir Ammar and Zahrani                                                                                                                                              
        Deir Ammar, 435/410 MW Expanded Deir Ammar with 870 MW capacity Addition of two gas and one steam turbine at Deir Ammar N None 2 2 $400   $139 $0.00 2.00% 40.00% 30.00 45.00% 15%   Low 2                                                                                                              
        2*145 MW gas turbines + 1*145 MW steam turbine   Addition of step-up transformers and associated electrical systems   None 2 2     $35 $0.00 0.50% 100.00% 40.00 5.00% 15%   Low 2                                                                                                              
        Zahrani, 435/410 MW Expanded Zahrani with 870 MW capacity Addition of two gas and one steam turbine at Zahrani   None 5 2 $400   $139 $0.00 2.00% 40.00% 30.00 45.00% 15%   Low 2                                                                                                              
        2*145 MW gas turbines + 1*145 MW steam turbine   Addition of step-up transformers and associated electrical systems   None 5 2     $35 $0.00 0.50% 100.00% 40.00 5.00% 15%   Low 2                                                                                                              
        Open cycle plants: 140/60 MW Open cycle plants: 0 Base MW                                                                                                                                                
        Baalbeck, 70/30 MW None (plant should play its role as peak rather than base plant)                                                                                                                                                
        Tyre, 70/30 MW None (plant should play its role as peak rather than base plant)                                                                                                                                                
        Hydroelectric plants: 221/40 MW, and efficiency at 80% Hydroelectric plants: 221/40 MW                                                                                                                                                
        Litani plants, 190/35 MW Same but with maintained capacity and improved performance Rehabilitation or the Litani plants     1 1     $7 $0.00 1.00% 100.00% 60.00 5.00% 10%   Low 2                                                                                                              
        Awali, 3*36 MW or 108 MW                                                                                                                                                  
        Joun, 2*24 MW or 48 MW                                                                                                                                                  
        Abdel Aal, 2*17 MW or 34 MW                                                                                                                                                  
        Al Bared, 17 MW None                                                                                                                                                  
        Al Bared 1, 3*4.5 MW or 13.5 MW                                                                                                                                                
        Al Bared 2, 1*1.2 MW + 1*2.5 MW or 3.7 MW                                                                                                                                                
        Richmaya, 13 MW None                                                                                                                                                
        Richmaya, 1*3.3 MW 1*6.8 MW                                                                                                                                                
        Kadisha, 25 MW None                                                                                                                                                
        Summary Summary                                                                                                                                                
        765 MW steam plants + 820 MW combined cycle plants + 60 MW open cycle plants + 40 MW hydroelectric plants = 1,685 MW 75 MW steam plants + 3,175 MW combined cycle plants + 0 MW open cycle plants + 40 MW hydroelectric plants = 3,290 MW (Base power) or (3,430 MW Peak power) -- Max Demand estimated at 2,900 MW by 2025 (refer to Maximum Demand Sheet)                                    
        Total for Generation Projects Required Within Short Term           $359                                                                                                                  
        Total for Generation Projects Required Within Medium and Long Term           $1,406                                                                                                                  
                                                                                                                                       
        Grand Total                 $0                                                                                                                                
        B. Transmission                                                                                                                                                  
                                             
        Overhead Lines Increased Lengths of the 66 kV systems                                                                                                                                                 
        30 km double circuit 400 kV overhead lines Same                                                                                                                                                
        380 km, double circuit 220 kV overhead lines (except for Deir Nbouh - Tartous line which is single circuit)  Expanded system as necessary  Installation of roughly 80 km of new 220 kV lines     1 2 $50   $35 $3.30 1.00% 20.00% 50.00 2.00% 20%   High 3                                                                                                              
          Upgraded Deir Nbouh - Deir Ammar line Upgrading of 30 km of 220 kV overhead lines      1 2 $50   $2 $0.00 1.00% 20.00% 50.00 2.00% 50%   Low 1                                                                                                              
        180 km, double circuit 150 kV overhead lines Same, to be gradually phased out                                                                                                                                                
        755 km, 66 kV single and double circuit overhead lines 1,000 km, 66 kV single and double circuit overhead lines  Installation of 245 km, 66 kV single and double circuit overhead lines    First phase before 2010 2 4 $300   $30 $8.19 1.00% 20.00% 50.00 2.00% 20%   Low 2                                                                                                              
        Underground Cables       Second phase before 2020 6 8 $300   $44 $9.06 1.00% 20.00% 50.00 2.00% 20%   Low 3                                                                                                              
        61 km, 220 kV XLPE insulated 3*single core underground cables 100 km, 220 kV XLPE insulated 3*single core underground cables (minor extensions for Beirut, new Pins-Aramoun circuit and connection to Ashrafieh) Installation of 40 km, 220 kV XLPE insulated 3*single core underground cables   None 5 1 $2,000   $78 $0.00 1.00% 100.00% 50.00 2.00% 20%   Low 2                                                                                                              
        11 km, 150 kV 2*3-core oil filled underground cables (Jamhour-Basta) 150 kV oil filled cables replaced by 220 kV XLPE circuits Installation of 22 km, 220 kV XLPE insulated 3*single core underground cables   None 4 1 $2,000   $44 $0.00 1.00% 100.00% 50.00 2.00% 20%   Low 2                                                                                                              
        17 km, 150 kV XLPE insulated 3*single core underground cables (Aramoun-Basta) 150 kV oil filled cables replaced by 220 kV XLPE circuits Installation of 17 km, 220 kV XLPE insulated 3*single core underground cables   None 6 1 $2,000   $34 $0.00 1.00% 100.00% 50.00 2.00% 20%   Low 2                                                                                                              
        14.5 km, 66 kV 2*3-core oil filled underground cables None (66 kV underground system for Beirut is expected to become obsolete)                                                                                                                                                
        7.5 km, 66 kV 3*3-core oil filled underground cables                                                                                                        
        19 km, 66 kV XLPE insulated 3*single core underground cables                                                                                                        
        22 km, 66 kV XLPE insulated 6*single core underground cables                                                                                                        
        6 km, 66 kV XLPE insulated 15*single core underground cables                                                                                                                                              
        Substations include                                                                                                                                                  
        (1) 400/220 kV substation (Ksara)  (5) substations in total and with some upgrades to existing  Construction of Tripoli and a further substation in the Provinces, and peformance of upgrades (addition of transformers, switchgear etc on 220 kV substations) Peform upgrades (addition of transformers, switchgear etc on 220 kV substations) To be performed on as needed basis                                                                                                                                          
        (1) 220/150 kV 120 MVA, 220/66 100 MVA, 150/66 30 MVA, 66/MV 40 MVA  (Deir Nbouh)                                                                                                                                          
        (1) 220/150 kV 200 MVA, 150/66 200 MVA, 66/MV 40 MVA  (Bsalim)                                                                                                                                          
        (1) 220/150 kV 100 MVA, 150/MV 140 MVA  (Aramoun) 5 5     $80 $2.25 1.00% 100.00% 50.00 5.00% 50%   Medium 3                                                                                                              
        (1) 220/66 170 MVA, 220/MV 70 MVA (Deir Ammar)                                                                                                                                          
        (3) 220/66 510 MVA, 66/MV 250 MVA (Zahrani, Ksara, and Halate)                                                                                                                                          
        (1) 220/MV 240 MVA, 66/MV 80 MVA (Commerciale)                                                                                                                                          
        (4) 220/MV 560 MVA   (Mkalles, Ras Beirut, Pins, and Saida (5) 220/MV substations Construction of Ashrafieh GIS substation and Baalbeck conventional substation   4 2     $50 $32.00 1.00% 100.00% 50.00 5.00% 50%   Low 1                                                                                                              
        (1) 150/66 160 MVA, 66/MV 110 MVA (Zouk) To be taken out of service Dismantlement of all equipment and delivery to EDL stores   None                                                                                                                                          
        (2) 150/66 600 MVA, 66/MV 140 MVA (Jamhour and Basta) Jamhour and Basta will be equipped with 220 kV system Add 220 kV switchgear in Jamhour and 220 kV GIS in Basta   None 7 2     $50 $0.00 1.00% 100.00% 40.00 5.00% 50%   Low 2                                                                                                              
        (1) 150/66 80 MVA (Jieh) 220/66 kV Switchyard Installation of new 220 kV equipment   In parallel with the Jieh project 5 2     $5 $0.00 1.00% 100.00% 50.00 5.00% 50%   Low 2                                                                                                              
        (54) 66/MV 2,400 MVA (several substations) (62) 66/MV substations  Construction and/or upgrading of (14) 66/MV conventional substations, in the Provinces   First phase before 2014 2 2 $6   $24 $1.50 1.00% 100.00% 30.00 5.00% 50%   Low 2                                                                                                              
              Second phase before 2020 5 10     $60 $4.50 1.00% 100.00% 60.00 5.00% 50%   Low 3  
        Summary Summary                                                                                                                                                
        220, 150, and 66 kV systems Expanded 220 kV and 66 kV systems                                   
        Total for Transmission Projects Required Within Short Term                 $52                                                                                                                                
        Total for Transmission Projects Required Within Medium and Long Term         $484    
        Grand Total         $535    
        C. Distribution                                                                                                                                                  
        C1. Medium and Low Voltage Network                    
                             
        Medium Voltage System includes approximately  Medium Voltage System to be increased by roughly 40%                                                                                                                                                
        15,000 transformers 21,000 transformers Installation of 7,000 transformers Installation of 7,000 transformers First phase before 2012 0 4 $12,000   $36 $0.00 1.00% 100.00% 40.00 2.00% 30%   Low 2                                                                                                              
                Second phase before 2020 4 10 $12,000   $48 $0.00 1.00% 100.00% 40.00 2.00% 30%   Low 3                                                                                                              
        12,000 km of overhead and underground cables, with the following voltages  Most of 11 kV systems to become 20 kV                                                                                                                                                
        11 kV (in Beirut)  To be replaced by 20 kV cables Installation of 700 km of 20 kV cables in Beirut   First phase before 2010 1 5 $100   $30 $0.00 1.00% 100.00% 40.00 2.00% 20%   Low 1                                                                                                              
                Second phase before 2015 6 8 $100   $40 $0.00 1.00% 100.00% 40.00 2.00% 20%   Low 2                                                                                                              
            Replacement of a few power transformers and distribution transformers in Beirut     0 2     $40 $0.00 1.00% 100.00% 40.00 2.00% 50%   Low 2                                                                                                              
        33 kV (limited parts in the North) To be replaced by 20 kV lines. Al Ouyon 33 kV substation will become a 66 kV substation. Replacement of insulators of overhead lines and replacement of some poles in the provinces     5 10     $10 $0.00 1.00% 100.00% 40.00 2.00% 50%   Low 3                                                                                                              
        20 kV (downtown Beirut, Zouk, and Beiteddine) Replacement of a few power transformers and distribution transformers in the provinces     5 10     $10           50%   Low 3                                                                                                              
        15 kV (in the provinces) Installation of 3,000 km 20 kV new overhead lines  First phase before 2012 1 5     $30 $0.50 1.00% 20.00% 40.00 2.00%     Low 2                                                                                                              
        5 kV (limted parts in the North)     Second phase before 2020 6 8     $60 $1.00 1.00% 20.00% 40.00 2.00%     Low 3                                                                                                              
        Radial MV system Loop MV system Upgrade to loops where possible      1 5     $15 $0.00 1.00% 20.00% 40.00 2.00% 50%   Low 1                                                                                                              
        Distribution in Zahle, Jbeil, and Aley are undertaken by independent concessions Same                                                                                                                                                
        Low Voltage System includes approximately Low Voltage System includes approximately                                                                                                                                                
        18,000 km of overhead and underground cables 25,000 km of overhead and underground cables, at 220/380 V  Installation of 7,000 km LV overhead lines and cables   First phase before 2012 0 5 $15   $45 $0.00 1.00% 30.00% 40.00 2.00% 20%   Low 2                                                                                                              
                Second phase before 2020 5 10 $15   $60 $0.00 1.00% 30.00% 40.00 2.00% 20%   Low 3                                                                                                              
        Summary Summary                                                                                                                                                
        Multiple voltage system with increased losses Unified 20 kV system with reduced losses                                
        C2. Consumer Connections                                   
                                             
        There are presently 1,100,000 subscribers (out of which are only 2,000 MV and 2 HV subscribers) Subscribers to increase by 40% (average 2.5% annually) and reach 1,500,000                                                                                                                                                 
        1,100,000 subscribers 1,500,000  subscribers Perform 400,000 new LV consumer connections with digital meters                                                                                                                                              
                First phase before 2010 0 5 $200   $20 $0.00 1.00% 40.00% 20.00 2.00% 50%   Low 1                                                                                                              
                Second phase before 2020 5 10 $200   $60 $0.00 1.00% 40.00% 20.00 2.00% 50%   Low 3                                                                                                              
        All LV subscribers are equipped with analog meters Most LV subscribers are equipped with digital meters Replacement of meters by digital systems on a gradual basis (project should be financed from O&M  budget)     1 15                     Medium 3                                                                                                              
        Total for Distribution Projects Required Within Short Term           $65                                                                                                                  
        Total for Distribution Projects Required Within Medium and Long Term           $439                                                                                                    
        Grand Total           $504                                                                                                    
                         
        Total for Electric Sector Projects Required Within Short Term                 $476                                                                                                                                
      Total Total for Electric Sector Projects Required Within Medium and Long Term                 $2,328                                                                                                                
        Grand Total                 $2,804                                                                                                                                
      Economic values   Present Values Future Values      
        Investment (a) 2,500 4,500      
        Land value / expropriation (a') 500 550      
        Yearly maintenance cost (b) 0.5% 2.5%      
        Major rehab/replac. cost (c ) 20.0% 20%      
        Span for rehab/replc (d) -- in years 5 12      
        Yearly operation cost (e) 4% 2%      
                                                                                                                                                           
      Institutional Setup            
        EDL is the monopoly provider of electricity, and it is a public sector company that reports to the Ministry of Energy and Water EDL should be a stronger and more autnomous institution, with younger and better trained staff Reinstatement of EDL’s privileges as an Independent Public Institution       
        EDL’s Board of Directors comprises presently five members, including the Chairman. The organization is composed of ten directorates, each headed by a director who reports directly to the General Director, who is also the Chairman. These directorates include  Reinforcement of EDL’s a