| Diesel | Dry Gas | Liquid Gas | Conclusions | |
| Cost of kWh in a combined cycle plant | 10 cents/kWh | 4 cents/kWh | 2.4 cents/kWh (high uncertainty factor due to unstable shipping costs, etc.) | |
| Generation Cost of 1,000 MW for 10 years | > 5 Billion Dollars | < 2.5 Billion Dollars | < 2.5 Billion Dollars | Theoretically Overall cost of LNG Plant may be recovered within less than 6 years if diesel is continued, yet unstable shipping costs, high capital investment, and high operation cost render the dry gas option more favorable in the present time. |
| Base value 1,000 MW for 10 years = 1000 MW x 1000 kW/MW x 24 hrs x 365 days x 10 years x 0.6 Load factor = 5.3x10^10 kWh | Generation using Diesel 5.3x10^10x0.1 = 5.3 Billion$ (excl maint) | Generation using Dry Gas 5.3x10^10x0.04 = 2.1 Billion $ (excl maint) | Generation using LNG 5.3x10^10x0.024 = 1.27 Billion $ | |
| Cost of LNG Plant = 300 Million$ | ||||
| Operation and Maintenance cost (20% annually) = 50 Million $/year x 10 years = 500 Million$ | ||||
| TOTAL = 1,272 + 300 + 500 = 2.1 Billion$ | ||||
| Loss Encountered as a Result of Loss of Largest Turbine in Nation | 218 MW | |||
| Actual Capacity in 2004 | 1,685 MW | |||